Tuesday, 12 March 2013

Mud, glorious mud


 The Friday team had finished the launder boarding last week, but there is still a lot of pointing to do.  As the pictures show, it wasn't the weather for it - snow, bitterly cold, and more of the same forecast.

So we started work on clearing the silt and leaves from the headrace.  Breaking the ice and scooping out 6 to 10 inches of slimy, smelly mud, and disposing of it down the bank, proved to be back-breaking work.
 At the end of  the day (or at least as much of it as we could cope with), we had done at least something towards clearing about 30 metres.  Just another 400 to go.

Tuesday, 5 March 2013

Reboarding the launder

 The launder is coming on nicely now, after Richard and others put in an extra day last Friday.  You can see in the picture how far they had got, and more progress was made today.  You can also see George in the background replacing the rail on the fence over the pit near the wheelhouse.

Peter and I continued preparing the larch boards for the launder, and brushing and painting the control lever for the gate valve.

The way the launder is being constructed can be seen here.  The side beams are 50mm thick oak, with the joining pieces made of the same and bolted on.  The bottom boards are 40mm thick larch, 40 inches long by about 10 inches wide (sorry about the mixed units, but those are the measurements that work!),  rebated 20mm x 20mm along each long edge to give a stepped joint.  The joints between boards and under the side beams are sealed with Roofer's Mate, which dries to a nice, inert, rubbery gasket.  The boards are screwed from underneath using Screwfix M8 x 70mm Turbo Coach Screws.  As you can also see in the picture, we have protected the core of the stone piers from any leakage water by reusing squares of the old plastic pond liner.

Wednesday, 27 February 2013

Solid progress with the launder

 I missed a week last week because of an achilles tendon injury, but back this week even if not fully mobile.  We had  a new starter, Peter, who spent the day helping me to prepare the bottom boards for the launder - putting the step in the edge of each one, cutting to length and drilling the 4 holes for the fixing screws.  This means there are now 44 of them, most of them ready for fitting in the launder, some with a few holes to drill.

Mike did a lot of (overdue) tidying in the wood store.

Richard and Ray did an extra day last week, as a result of which the launder side beams were fully in place complete with joining pieces.
This week they set about restoring the sluice end of the launder.  The uprights were dowelled to the ends of the side beams...

 ... before the second upright was rebated and screwed into place.  These two make the slot in which the vertical blade shutter runs.
Finally the blade and the hinged "gate valve" were re-installed.  The mechanical parts of the launder are therefore almost complete.

Tuesday, 12 February 2013

Progress at last

The side supports tested in place, and
 hessian sacks cover the new mortar
At last the weather has been kind enough to allow us to move forward with the launder.

George repointed some of the launder piers' stonework  and began to rebuild the spillway. The mortar will need to be protected by hessian sacks from some of the frosts we are expecting over the next day or so.

Richard cut the new spillway stone to size; in that way bits of stone have, it also broke into two pieces, which will need to be thought about when we cement it/them in.  He carried on preparing the spillway end for building the launder.

Ray and Bob cut the steps into the edges of 20 of the larch boards for the bottom of the launder and trimmed them to length.

Finally we arranged two of the side supports for the sluice end of the launder, checked with a string line that they were lined up with the other end, and fixed one of the bottom boards.

Tuesday, 5 February 2013

Progress slow in the snow

The view from the mill in the heaviest snow
 Pretty, isn't it?  But a darned nuisance - apart from the difficulty of working in snow, we need to point the piers before we can begin building the launder, and we can't use the lime mortar below 5 degrees C.

Nonetheless, we did get some cleaning up done ready for the weekend opening of Acorn Bank this weekend, putting tools away and helping Sara to sweep the mill room.  We also managed to do some work on the piers, and repair the two tarpaulin covers we put up last week, just before it got very windy!
The launder having been removed, there was no fence between the public path and the space under and beyond the launder.  The visiting public needed to be protected from the hazards of these areas, especially alongside the steps.  Richard and I dismantled the rough crate that the lime mortar was delivered in, and reassembled the bits to make a crude but effective fence.

Tuesday, 29 January 2013

Working outside in bad weather

The hydraulic lime we ordered last week had actually arrived; we had to store it up at the house to protect it from frost.  The scaffolders had been to amend the end fence so we can now get to the spillway stonework, so work on the launder can begin.  However, the weather is alternately frosty and wet, neither of which suits the lime mortar, so we put up a couple of plastic sheets to keep the rain off.  It has been very windy since...
 A group of conservation people from Sizergh were working at the house, and they wanted to be shown round the mill; naturally we obliged.  We also did some minor chores - including continuing to sort our huge collection of mixed screws by size!!!!


Tuesday, 22 January 2013

Winter weather

Some of the parts of the second waterwheel

 It has been a bit nippy these past 2 Tuesdays, so progress on the launder has been rather slow.  However, last week the scaffold had been erected, though not exactly as we wanted it.  It is much safer working between the launder and the spillway pit, but they have put a fence at the spillway end which prevents us getting to the stonework.
We were therefore at least able to do a  few preparatory jobs.  There is also a project to restore the mill barn, so we had to remove a few mill artifacts from it - such as the shroud plates from the second waterwheel.  These may not look much, but need 3 men to move them safely.
George and Richard clean up
the spillway

Today there was no Ray, as he was digging his car out of the snow.
We all helped to remove the large old, delaminating stone from the edge of the spillway, remove the loose stones below it, and tidy up the mortar. George carried on tidying up the stones and mortar in the general launder area.  We seem to have acquired a suitable replacement for the top stone from the former greenhouse floor.  Ian, the Trust buildings man, has approved the lime mortar we plan to use to rebuild the spillway, so this can now go ahead.


Bob and Richard mounted the two new pulley brackets for the revised sack hoist.  Richard had fabricated them to the measurements Bob took a few weeks ago, and they were painted last week.  Everything went together without too much of a problem.

Richard fixes the pulley bracket; note the
rare glimmer of sunshine!