Tuesday, 2 July 2013

Catching up!

 Sorry not to have posted anything for a few weeks, but life has been rather busy both at home and in the mill.
We have been milling (and selling) a lot of flour - failing to get far enough ahead of ourselves to deliver any to the shop.

The ash spring on the shoe broke, so we have reinforced it with a metal coil spring.  The photo also shows the "sock" we have added to the shoe (!) to prevent grains bouncing off the damsel and over the stones, ending up whole in the flour.
On May 18th the river rose so fast that Richard had to stop the mill turning to prevent damage.  A lot of the pond liner in the wheel buckets stripped out, so Bob and (mostly) Ray replaced them the following Tuesday.


Meanwhile, work has continued on the drive for the shelling stones.  The steel plates have been finished and bolted to the stone nut - here Ray and Richard are drilling the top plate for the insertion of spring pins to help take the rotational force.
The cob oven is no more
  Work is supposed to be starting soon to restore the mill barn, so we have been busy removing everything important from its inside and immediate outside.  This includes several thousand roof slates, a huge amount of stone, the stone lintel beams for the kiln and, unfortunately, the cob oven.  Peter Dickens says he will build a new and better one when the barn is finished.

Saturday, 4 May 2013

The Independent on Sunday Happy List

Another accolade for the mill volunteers.  Last Sunday the Independent on Sunday published its "Happy List" of 100 people "whose volunteering, caring, fundraising, mentoring, charity founding or selflessness makes Britain a more contented, supportive, better-adjusted and happier place."   And the Acorn Bank Watermill volunteers were first (alphabetically) in the list!

Our entry reads: 
"Acorn Bank Watermill Volunteers
Heritage lovers
Richard Harland, Ray Gill and Bob Price form the trio who painstakingly restored and now maintain an ancient mill at Temple Sowerby, Cumbria. For five years they have helped to rebuild the wooden structure, and the mill is now able to grind flour for the first time in over 70 years."

The full article can be seen at

http://www.independent.co.uk/news/people/news/the-independent-on-sunday-happy-list-2013-8591000.html

Tuesday, 30 April 2013

Tidying up and getting ready to mill

A full house today, Richard, Ray, Bob, George, Mike and Peter. Between us we tackled some finishing-off jobs.

The information board explaining the Lower Mill Machinery had fallen off the fence and needed to be re-displayed.  We had been thinking for some time that it was in the wrong place, as visitors saw it on entering the mill and thought it referred to the main machinery.  Ray and Bob decided to make a stand for it so it would be more relevant.

They then went on to repair part of the fence on the viewing platform.
 George and Mike carried on pointing and replacing the cobbles where we had inserted the new fence above the spillway pit.  In the previous couple of weeks when I wasn't there, the volunteers built a new trough to catch the water spilling from the dump valve.  Peter can be seen here extending and lining it.

Richard meanwhile got the machinery set up and ready to start milling. At the end of the afternoon the year's first delivery of wheat arrived and had to be manhandled across the yard and upstairs.  Not good for the back - we must get the sack hoist working.
We also put the cob oven back into some kind of usable state.  We had rather neglected it, because it would have had to be rebuilt when the barn was restored, but that project has been held up by the possibility of bats.  We cleaned it up, fitted a new tarpaulin and George skinned the outer surface with fresh lime mortar.

Wednesday, 3 April 2013

Tidying up the launder area

The launder has gone together slightly different that the previous version, so we have had to make one or two adaptations, including to the gate valve.

We have now finished the work on the launder, apart from the pointing (which we still can't do as the weather remains stubbornly below the required 5 degrees) and stopping up one or two leaks (also difficult at present temperatures).  It has been the coldest March for 66 years, apparently.

We therefore began tidying up by removing a lot of the rubble, sacks and bags we had been using or had left about. We also began to replace and repair the fencing.  As you can see, the section of fence alongside the steps is now back in place, as is the guard rail for the gate valve adjusting platform and part of the temporary fence has been removed.

Tuesday, 26 March 2013

Easter coming up, and still snowing

We were joined today by a new mill volunteer - welcome, Lesley! She rapidly got stuck in to cleaning and tidying part of the workshop. Ray was still snowed in in Weardale.

Meanwhile we managed to do some finishing off outside.  We replaced the little bit of fence from the launder to the wall next to the kiln door (back left corner of this picture) and finished off the new fence between the launder and the spillway pit.

George re-bedded the new spillway stone, which had come adrift in the frosts.  We generally tidied things up, hoping to be able to turn the machine over Easter weekend.  We will not be milling for a few more weeks.

We also completed the flour desiccation test - we bagged 1532g of flour in June 2012 and I have kept it at home to see how much weight it loses by drying out over its 6 month shelf life.  We meant to weigh it again in December, but weather and other stuff was against us, so we did it today and interpolated the weight at 6 months.  It was OK, so we know we need to continue bagging 1530g of flour in our 1.5kg bags.

Tuesday, 19 March 2013

Mud and fencing

 Today the estate staff (Robert, Sam the lone ranger, and Jim the volunteer) cleared muck from the major part of the headrace.  Here you can see the resulting mucky bank.

There was no Ray (snowed in again), but the rest of us got on with fitting the metal post sockets for the new fence alongside the spillway pit.

 

Tuesday, 12 March 2013

Mud, glorious mud


 The Friday team had finished the launder boarding last week, but there is still a lot of pointing to do.  As the pictures show, it wasn't the weather for it - snow, bitterly cold, and more of the same forecast.

So we started work on clearing the silt and leaves from the headrace.  Breaking the ice and scooping out 6 to 10 inches of slimy, smelly mud, and disposing of it down the bank, proved to be back-breaking work.
 At the end of  the day (or at least as much of it as we could cope with), we had done at least something towards clearing about 30 metres.  Just another 400 to go.